September - 2017 Placement of concrete drain wells and pipe racks

The contractor is continuing the construction of the Ecluse network. A lot of work has been done at the INEOS Phenol site, where the piping will be placed underground. Over the past few months, the contractor has laid more than 50% of the transport network on-site.
 
Concrete drain wells have been placed at the site of DP World and a few public areas. These drain wells serve as a juncture between underground and above-ground sections of the pipeline.
 
At the sites of Indaver, Lanxess, Momument Chemical and in public areas, preparations have been made for the installation of pipe racks.
 
The welding work is now in full progress both behind Fort Liefkenshoek and towards the Lanxess site. In the next few weeks, the elevation of the expansion loops will begin, along with the connection of the different network components.

July 2017 - Welding behind Fort Liefkenshoek

 

The last couple of months the contractor has been busy with preparatory work alongside the 'Ketenislaan', the 'Geslecht' and behind the Fort Liefkenshoek. After levelling, pile driving and placing the sleepers, the welders started the first welding jobs for the construction of this part of the Ecluse route. The piling of the poles on the route has been completed,  screw piles still need to be screwed into the ground on some places on the Ecluse route. The screw piles will for instance be used to support the new  pipe bridge, which will be placed across the railway alongside the Geslecht.

 

 

May 2017 - The piling of the poles

On May the 2nd, the contractor started the piling of the poles at the rear of the sites of INEOS Phenol, ADPO and Monument Chemical. The work will then move along the Ketenislaan for the rest of this route. The placing of the poles on this part of the route will take about 5 weeks. The steel tube poles are placed at a depth of 14 to 20 meters. These poles will serve as the foundation for the installation loops and expansion loops. The 'Waaslandhaven' port area used to consist of fertile polders, so a solid foundation is essential for stability. Extension loops are provided to accommodate fluctuations in temperature in the steel pipelines. At the same time, preliminary groundwork will be carried out for the placement of the concrete sleepers that will support the pipelines. Approximately 240 poles, 660 sleepers and 15 pipe bridges will be put in place for the entire project.

March 2017 - Placement of temporary buildings

In March, in preparation for the delivery of the steam network components, two temporary buildings were constructed on the sites near Monument Chemical.

 

One plot is intended for storage of the materials, the other to prepare all the pipelines. The pieces will be merged, welded and finished once they have been delivered to Doel.